| COMPLETED PROJECTS | ONGOING PROJECTS |
|---|---|
| Construction of Viaduct from Km 36.062 to Km 38.262 of Right Main Canal of Vamsadhara Project. | Formation of Left Side Flood Bank from Km 22.000 (near N.H Bridge) to Km 37.100 and R/s Flood Bank from Km 22.000 to Km 39.000 (Near N.H Bridge) of Swarnamukhi River in SPSR Nellore District (SW- 2). |
| Improvements to 4 Nos of Aqueducts in Reach-I of K.C. Canal (Package No. ICB-07A). | Lining of Existing SRBC/GNSS canal upto berm level to draw 30000 Cusecs in between Gorakallu Reservoir to Owk Reservoir including Owk Tunnel III |
| Formation of D bund (balance portion) including protection works from Km. 0.00 to Km. 0.900 of TGP main canal. | Permanenet Restoration to Survepalli Rservoir near Iskapalem villages limits in Venkatachelam Mandal of SPSR Nellore District. |
| Excavation and construction of surplus escape for subsidiary Reservoir-II of TGP Main canal. | Formation of Flood banks along the Mogameru vagu near Animela (Vi) in V.N. Palli (M), Y.S.R District. |
| Construction of river training walls on left and right flanks of Nagarjuna Sagar Tail Pond Dam across river Krishna near Satrasala(V), Guntur District. | HNSS Project Phase-II-Package- 21, Earth work excavation of Main Canal in Kadapa District of Andhra Pradesh |
| APILIP-JBIC-Modernization of Canal System and System tanks under Lower Sagileru Project (Medium Irrigation) in Kadapa District. | Construction of Althurupadu Balancing Reservoir, 3 Nos of O.T Sluices, 2 Nos of Inlets and Out fall regulator near Althurupadu village of Dakkili Mandal of SPSR Nellore District |
| Modernization of Araniar Project near Pitchatur Village and Mandal, Chittoor District. Dredging works in Krishna & Godavari Delta in Krishna, Guntur, E. Godavari and W. Godavari Districts. |
Somasila proj-Anam Sanjeeva Reddy High Level Lift Canal Phase-II - Construction of Two (2 Nos) Balancing Reservoirs, Gravity Canal including CM&CD works, one lift on Balancing Reservoir IV including construction of Pump House, Procurement, Erection Testing and Commissioning of Electro-mechanical, Hydro-Mechanical and Pressure Mains for creatioin of IP for 46,453 acreas ayacut in Duttalur, Vinjamur,Udayagiri and Marripadu Mandals in SPSR Nellore District-Phase-II Works |
| Rehabilitation and Modernization of Canals Distributory system of Nagarjunasagar Lal Bahadur canals | Formation of Flood banks along the Mogameru vagu (Gurrappa Yeru) near Nallacheruvupalli (Vi), Vemula (M), Y.S.R District. |
| Rehabilitation and Modernization of Canals Distributory system of Nagar-junasagar.0675 Lal Bahadur & Jawaharlal Nehru Canals, A.P. | Formation of Flood banks along the Mogameru vagu near Nallacheruvu palli village in Vemula Mandal of Y.S.R District |
| Rehabilitation and Modernisation of Distributory system under musunnur Distributory Committee of NSLBC, AP, India ( Pkg.No.LC-KRI-Dc 32) | Formation of Flood banks along the Mogameru vagu near Kondreddy palli village in Vemula Mandal of YSR District |
| COMPLETED PROJECTS | ONGOING PROJECTS |
|---|---|
| Construction of Aqueduct across Peddavagu @ Km. 16.150, of Flood Flow Canal from S.R.S.P in Karimnagar District. | Re-Engineering of IFF Canal Project Formation of Gouravelly Reservoir capacity 1.410 to 8.23 TMC near Gouravelly (Village), Husnabad (Mandal),of Karimnagar District. |
| S.B.B.R –Construction of OGEE spillway from Km. 0.668 across Maganur Vagu in Mahaboobnagar District. | Construction of Dindi Balancing Reservoir of SLBC Tunnel Scheme across Dindi river near Mothia Thanda of Teldevarapalli (V), Chandampet (M), Nalgonda District. |
| Formation of earth dam of Jonnalaboguda balancing reservoir from km.0.450 of Kalwakurthy lift irrigation scheme Mahabubnagar District. | Palamuru Rangareddy Lift Irrigation Scheme- (Package No. 13) - Formation of Earthen Embankment of Kurumurthiraya Reservoir from Km 0.00 to Km. 4.50 near Karvena (V), Boothpur (M), Mahabubnagar District. |
| Formation of Earth Dam from Km.1.900 across Maganurvagu near Sangambanda (V), Makthal (M), Mahaboobnagar District. | SRSP – Stage 1- Package-XV - Modernization and Lining of D/28 and Palkeri vagu anicut and its minors and sub minors of Saraswathi Canal, Khanapur (M), Nirmal District |
| APILIP-JBIC-Modernization of Dindi Medium Irrigation Project, Dindi Village and Mandal, Nalgonda District. | SRLIP-Package No. 2-Execution of Gravity Canal from Km. 10.800 near BG Kotturu (V), Aswapuram (M) to Km. 32.000 near Vepalagadda (V), Burgampahad (M), Khammam Dist. including CM & CD works etc. |
| Formation of New Tank across local stream near Itikyala (V), Asifabad (M), Adilabad District. | SRLIP-PKG 12- Sathupally Trunk- Earthwork excavation, forming embankment and construction of CM&CD works, CC lining for formation of Palavagu Branch Canal from Km 1.925 near Gandugulapally(V) to Km 13.500 near Arlapenta(V), Gollagudem Distributory from Km. 13.500 near Alapenta (V) to Km 31.875 at Malkaram(V) of Dammapeta (M) and Vinayakapuram Distribvutory from Km 0/0 near Arlapenta (V) of Dammapeta (M) to Km 23.850 near Vinayakapuram(V) oflAswaraopeta (M) in Bhadradri Khammam District. |
| Rehabilitation and Modernization of Canals Distributory system of Nagarjunasagar Lal Bahadur canals | SRSP – Stage 1- Package-XIV -Modernization and Lining of D/27 and its minors and sub minors of Saraswathi Canal, Khanapur(M), Nirmal District |
| ADILABAD DISTRICT-Lower Penganga Project- Excavation and Lining of Main Canal from 47.00 Km to 89.09 Km including Costruction of Structures | |
| Medium Irrigation - Construction of additional Works of Peddavagu Diversion Scheme near Jagannathpur (V), Kaghaznagar (M), Kumram Bheem Asifabad District. |
| COMPLETED PROJECTS | ONGOING PROJECTS |
|---|---|
| Formation of a reservoir across Cheyyar river near Kuppanatham village with allied component works diversion road, construction of cross masonry works | |
| Construction of Rubble mound seawell along Ennore Expressway in North Chennai for a length of 2270m (LS 12/6800 to 13/950 & 14/280 to 14/740 & 14/960 to 15/200Km) | |
| Improvements to South Buckingham Canal like widening, Deepining of water ways of bridge from Okkaiyam Maduvu to muttukadu back waters (North Lock) from LS10500m to 2300 m (Reach -3) Eastern Basin package -6 |
| COMPLETED PROJECTS | ONGOING PROJECTS |
|---|---|
| Construction of Earth Dam (Left Flank) of RET Irrigation Project in Bhawanipatnam. | Construction of Earth Dam (Right Flank) of RET Irrigation Project in Bhawanipatnam. |
| S.No. | Name of work | Client | Client Value in Rs. Millions | Year of Completion |
|---|---|---|---|---|
| 1. | Construction of Aqueduct across Peddavagu @ Km 16.150, Earth Work Excavation 15,000 to Km.15.985 and From Km. 16.325 to Km.17.000 of Flood Flows Canal from SRSP. | Superintending Engineer, SRPS, FFC Circle, Jagityal | Rs. 1217.70 | July, 2008 |
| 2. | Improvements to South Buckingham Canal like Widening Deepening, Widening of Water ways of Bridges from Okkiyam Maduvu to Muttukadu Back Waters (North Lock) from LS 10500m to 23500m. | Superintending Enginer, Palar Basain Circle, Chepauk, Chennai. | Rs. 835.14 | December, 2014 |
| 3. | Rehabilitation and Modernisation of Distributory system under Musunuru Distributory committee of Nagarjunasagar9 Lal Bahadur Canal, A.P.India Pkg No. LC- KRI-DC-32. | The Superintending Engineer, NSLBC, O&M Circle, Tekulapally, Khammam District. | Rs. 466.36 | October, 2018 |
| 4. | Construction of Earth Dam (Left Flank) of RET Irrigation Project in Bhawanipatnam. | EE, RET Irrigation Division, Bhavanipatnam. | Rs. 305.25 | May, 2016 |
| 5. | Formation of Reservoir across Cheyyar River near Kuppanatham Village with allied Component Works. Diversion Road and Construction of cross masonry works in Chengam Taluk of Tiruvannamalai District. | Superintending Engineer, PWD WRO, Project Circle,Vellore, Tamilnadu. | Rs. 257.28 | August, 2008 |
| 6. | JBIC-Modernization of Canal System and system tanks under Lower Sagileru Medium Irrigation Project in Kadapa District. | Superintending Engineer, I&CAD, Irrigation Circle, Kadapa. | Rs. 233.79 | June, 2016 |
| 7. | Minor Irrigation-J.I.C.A-Batch-III-Formation of New Tank across local stream near Itikyala (V), Asifabad (M), Adilabad (Dist). | Superintending Engineer, I & CAD, Dept., MIP Circle Bellampally. | Rs. 219.31 | September, 2016 |
| 8. | - Construction river training walls on left and right flanks of Nagarjuna Sagar Tail Pond Dam across river Krishna near Satrasala(V), Guntur Dt. A.P. | SE/CIVIL, NTPDC, AP GENCO, Nalgonda District. | Rs. 168.80 | December, 2013 |
| 9. | S.B.B.R. - Construction of OGEE Spillway from Km. 0.668 to Km. 0.834 N.O.F. Blocks from Km. 0.648 to Km. 0.668 Head Regulator at Km. 0.575 and formation of left Earth Dam from Km. 0.555 to Km. 0.648 and Right Earth Dam from Km. 0.834 to Km. 1.00 across Maganur Vagu. | Superintending Engineer, BLIP Circle, Pebbair. | Rs. 146.06 | May, 2003 |
| 10. | Construction of Viaduct from Km. 36.062 to Km.38.262 of Right Main Canal of Vamsadhara Project. | Superintending Engineer, Vamsadhara Project Circle, Srikakulam. | Rs. 144.91 | February, 2006 |
| 11. | Formation of Earth Dam of jonnalaboguda Balancing Reservoir from Km 0.450 to Km 0.850 including Earth Work, Excavation & Forming Embankment of Gravity Canal from Km 8.000 to Km 9.000 of Kalwakurhy Lift Irrigation Scheme, Mah abubnagar District. | Superintending Engineer, NKLISI Circle, Mahabubnagar. | Rs. 131.40 | September, 2006 |
| 12.. | Rehabilitation and Modernisation of Distributory system under Distributory committee No.5, Piduguralla of Nagarjunasagar Jawahar Canal, Andhra Pradhesh. India vide Package No. RC-GNT- DC-37. | Superintending Engineer, NSJC, O&M Circle, Lingamguntla, Narsaraopet, Guntur District. | Rs. 116.83 | March, 2017 |
| 13. | Rehabilitation and Modernisation of Distributory system under Janapadu Distributory committee of Nagarjunasagar Lal Bahadur Canal, A.P.India Pkg No. LC-NLG-DC-5. | Superintending Engineer, NSLBC, O&M Circle, Miryalaguda, Nalgonda District. | Rs. 129.42 | |
| 14. | Rehabilitation and Modernisation of Distributory system under committee of Nagarjunasagar Lal Bahadur Canal, A.P.India Pkg No. RC- GNT-DC-52 | Superintending Engineer, NSLBC, , Lingamguntla | Rs. 78.48 | June, 2017 |
| 15. | Rehabilitation and Modernisation of Distributory system under committee of Nagarjunasagar Lal Bahadur Canal, A.P.India Pkg No. RC- PRA-DC-38 | Superintending Engineer, NSLBC, , Lingamguntla | Rs. 153.85 | March, 2017 |
| 16. | Rehabilitation and Modernisation of Distributory system under committee No.9,CHAMARRU of Nagarjunasagar Lal Bahadur Canal, A.P.India Pkg No. RC- GNT-DC-41 | Superintending Engineer, NSLBC, , Lingamguntla | Rs. 67.176 | November 2015 |
| 17. | Rehabilitation and Modernisation of Distributory system under committee No.17,Guntur of Nagarjunasagar Lal Bahadur Canal, A.P.India Pkg No. RC- GNT-49 | Superintending Engineer, NSLBC, , Lingamguntla | Rs. 128.19 | July 2017 |
| 18. | Rehabilitation and Modernisation of Distributory system under committee No.24, Rompicherla of Nagarjunasagar Lal Bahadur Canal, A.P.India Pkg No. RC- GNT-DC-56 | Superintending Engineer, NSLBC, , Lingamguntla | Rs. 132.18 | June 2017 |
| 19. | Rehabilitation and Modernisation of Distributory system under committee No.28,inavolu of Nagarjunasagar Lal Bahadur Canal, A.P.India Pkg No. RC- GNT-DC-60 | Superintending Engineer, NSLBC, , Lingamguntla | Rs. 70.39 | July 2016 |
| S.No. | Name of work | Client | Value in Rs. Millions |
|---|---|---|---|
| 1. | Re- Engineering of IFFC Project from SRSP Formation of Gouravelly Reservoir with enhanced capacity of 1.410 to 8.23 TMC water including Construction of HC Weir Formation of Diversion Road including Construction of DLR Bridge, Investigation Designing and Estimation, near Gouravelly (V), Husnabad (M), Karimnagar (Dist) | Superintending Engineer, FFc, Circle-II,LMD Colony, Karimnagar. | Rs. 5832.77 |
| 2. | Somasila proj-Anam Sanjeeva Reddy High Level Lift Canal Phase-II - Construction of Two (2 Nos) Balancing Reservoirs, Gravity Canal including CM&CD works, one lift on Balancing Reservoir IV including construction of Pump House, Procurement, Erection Testing and Commissioning of Electro-mechanical, Hydro-Mechanical and Pressure Mains for creatioin of IP for 46,453 acreas ayacut in Duttalur, Vinjamur,Udayagiri and Marripadu Mandals in SPSR Nellore District-Phase-II Works | Superintending Engineer, Somasila Project Circle, Nellore | Rs. 4596.31 |
| 3. | Construction of Dindi Balancing Reservoir of SLBC Tunnel Scheme across Dindi river near Mothia Thanda of Teldevarapalli (V), Chandampet (M), Nalgonda District. | Superintending Engineer, AMRSLBCP Circle No. 1, G.V.Gudem, Nalgonda. | Rs. 2741.20 |
| 4. | Palamuru Rangareddy Lift Irrigation Scheme- (Package No.13)- Formation of Earthen Embankment of Kurumurthiraya Reservoir from Km. 0.00 to Km. 4.50 near Karvena (V), Boothpur (M), Mahabubnagar District. | Superintending Engineer, I & CADD, PRLIS Circle No.1, Nagarkurnool. | Rs. 2363.36 |
| 5. | SRLIP-Package No. 2-Execution of Gravity Canal from Km. 10.800 near BG Kotturu (V), Aswapuram (M) to Km.32.000 near Vepalagadda (V), Burgampahad (M), Khammam Dist. including CM & CD works etc., | Superintending Engineer, Dummugudem Project Circle, Tekulapally, Khammam. | Rs. 1885.67 |
| 6. | Construction of Althurupadu Balancing Reservoir, 3 Nos of O.T Sluices, 2 Nos of Inlets and Out fall regulator near Althurupadu village of Dakkili Mandal of SPSR Nellore District. | Superintending Engineer, SSLC &SB Circle, Nellore. | Rs.1859.62 |
| 7. | SRLIP-PKG 12- Sathupally Trunk- Earthwork excavation, forming embankment and construction of CM&CD works, CC lining for formation of Palavagu Branch Canal from Km 1.925 near Gandugulapally(V) to Km 13.500 near Arlapenta(V), Gollagudem Distributory from Km. 13.500 near Alapenta (V) to Km 31.875 at Malkaram(V) of Dammapeta (M) and Vinayakapuram Distribvutory from Km 0/0 near Arlapenta (V) of Dammapeta (M) to Km 23.850 near Vinayakapuram(V) oflAswaraopeta (M) in Bhadradri Khammam District. | “Superintending Engineer & Project AdministratorSita Rama Lift Irrigation Project - 2Khammam." | Rs. 1523.60 |
| 8. | Investigation, Design and execution of Mothe Vagu Reservoir including all other allied works across Mothe Vagu near Koratpalli(V), Ramadugu (M) of Karimnagar District. | SE, IFFC Circle-1, Dharoor Camp, Jagtial. | Rs. 1398.08 |
| 9. | Formation of Left Side Flood Bank from Km 22.000 (near N.H Bridge) to Km. 37.100 and R/s Flood Bank from Km 22.000 to Km 39.000 (Near N.H Bridge) of Swarnamukhi River in SPSR Nellore District (SW-2). | Superintending Engineer, Irrigation Circle, Nellore. | Rs. 664.61 |
| 10. | Lining of Existing SRBC/GNSS canal upto berm level to draw 30000 Cusecs in between Gorakallu Reservoir to Owk Reservoir including Owk Tunnel III | Superintending Engineer, SRBC Circle No.2,Nandyal, Kurnool District. | Rs. 259.55 |
| 11. | SRSP – Stage 1- Package-XIV -Modernization and Lining of D/27 and its minors and sub minors of Saraswathi Canal, Khanapur(M), Nirmal District. | Superintending Engineer, GVC No.1, Sriramsagar Project, Pochampad (V) , Mendora (M), Nizamabad District. | Rs. 144.05 |
| 12. | SRSP – Stage 1- Package-XV - Modernization and Lining of D/28 and Palkeri vagu anicut and its minors and sub minors of Saraswathi Canal, Khanapur (M), Nirmal District. | Superintending Engineer, GVC No.1, Sriramsagar Project, Pochampad (V) , Mendora (M), Nizamabad District. | Rs. 122.82 |
| 13. | Permanenet Restoration to Survepalli Rservoir near Iskapalem villages limits in Venkatachelam Mandal of SPSR Nellore District. | SE, Irrigation Circle, Nellore | Rs. 94.03 |
| 14. | HNSS Project Phase-II- “Package- 21, (Balance Work) Earth work excavation of Main Canal from Km. 511.000 to Km.523.450/523.000 including construction of CM & CD works” in Kadapa District of Andhra Pradesh. | Superintending Engineer, H.N.S.S. Circle No.3, Madanapalle. | Rs. 89.78 |
| 15. | Formation of Flood banks along the Mogameru vagu near Animela (Vi) in V.N. Palli (M), Y.S.R District. | The Superintending Engineer, Irrigation Circle, Kadapa. | Rs. 57.80 |
| 16. | Formation of Flood banks along the Mogameru vagu near Nallacheruvu palli village in Vemula Mandal of Y.S.R District. | The Superintending Engineer, Irrigation Circle, Kadapa. | Rs. 39.95 |
| 17. | Formation of Flood banks along the Mogameru vagu near Kondreddy palli village in Vemula Mandal of YSR District. | The Superintending Engineer, Irrigation Circle, Kadapa. | Rs. 39.84 |
| 18. | Formation of Flood banks along the Mogameru vagu (Gurrappa Yeru) near Nallacheruvupalli (Vi), Vemula (M), Y.S.R District. | The Superintending Engineer, Irrigation Circle, Kadapa. | Rs. 30.60 |